Dry Dock and Special survey of Sea Falcon
A 3 months alongside/ dry
dock repair was carried out for Sea Falcon in preparation for its 25
years special Survey. Repair works include 50 tonne of steel work
renewal of cargo tank, cargo pump, pipe lines, access platform and fresh
water tank to NIPPON KAIJI KYOKAI Classification (ClassNK). For the
survey, the propeller shafts had to be withdrawn and both the sea chest
valves and machinery overhauled. As part of the project, tank cleaning
was carried out to meet inspection requirement. The vessel was also dry
docked for water work repair, blasting to SA 2.5 and eventually received
a paint work. The project was completed for Seven Seas.
|